Today the final pile was inserted through the pool floor, and the piling rig has been removed from within the swimming pool structure.
Each pile will now be cut down to the correct length, a reinforcement rod inserted down to the base of the pile and await the arrival of the cement pump over lorry, which will hopefully arrive on Wednesday this week. Cement will then be poured down each pile tube to create a pillar which will support the new floor.